Improving soil, Roads, Car parks, infrastructure works & transformer substations at the North Sulaibkhat Housing Project.
Fields of Activity:
Civil & Infrastructure
Clients:
Public Authority for Housing Welfare
Contract No.:
PAHW/C/1139/2009-2010
Project Value (KD):
36,229,970
Commencement Date:
Oct 13, 2009
Completion Date:
May 30, 2012
Project Description:
Treatment & improving the weak soil properties of the whole area of the project and area comprehensive residential buildings and construction, completion and maintenance of roads and parking area, networks of infrastructure services and demarcation of 1426 plots, 62 residential areas, 35 electrical transformer substations Model 4 + 17 electrical transformer substations Model 2 for northwest of Al-Suliabikat housing. The total area of the Project comprises of 2,568,000 Sq. Mtr.