Doha West Sewage Treatment Works - Extension No. 3 (Main Contractor Degremont & Marubani)
Fields of Activity:
Treatment Plants and Pumping Stations
Contract No.:
DTC 0075 D1
Project Value (KD):
22,480,698
Commencement Date:
Feb 13, 2006
Completion Date:
Aug 31, 2008
Project Description:
The Work comprises the design, construction, operation and maintenance of the transfer pumping stations, gravity sewers and pumping mains, sewage treatment works and treated sewage effluent return main from The Pearl-Qatar to the new treatment plant located some 10km to the north east of The Pearl. The principal elements of the Works to be designed and constructed include, but are not necessarily limited to the following and their associated buildings and controls l A new raw sewage pumping station l Modification of an existing raw sewage pumping station l 10km of gravity sewers and pumping mains l Membrane Biological Reactor (MBR) sewage treatment works l Treated sewage effluent (TSE) pumping station l 10km of TSE pumping main