Completed

Excavation, Dewatering, Diaphragm Wall & Temporary Works - Plot No. P-20, Sectors E1 and E2, Abu Dhabi Central Market Redevelopment

Clients:
ALDAR Properties PJSC
Contract No.:
22C
Project Value (KD):
8,320,000
Commencement Date:
Jul 20, 2005
Completion Date:
Jul 19, 2006

Excavation, Dewatering, Diaphragm Wall & Temporary ...

Read More

Sea Outfall Culverts at North Doha

Clients:
Ministry of Public Works
Contract No.:
RA/97
Project Value (KD):
5,809,030
Commencement Date:
Apr 26, 2004
Completion Date:
Apr 25, 2006

Sea Outfall Culverts at North Doha

Read More

Infrastructure of the Amgharah Area

Clients:
Public Authority for Industries
Contract No.:
PAI/7
Project Value (KD):
7,984,000
Commencement Date:
Apr 20, 2004
Completion Date:
Apr 20, 2006

Infrastructure of the Amgharah Area

Read More

Al-Salam District, South Surra - Roads & waste water drainage

Clients:
Ministry of Public Works
Contract No.:
RA/67
Project Value (KD):
9,242,959
Commencement Date:
Jul 03, 2002
Completion Date:
Sep 15, 2004

Al-Salam District, South Surra - Roads & waste water ...

Read More

Pump Station, Reservoir, Administration Building and Main Transfer Lines of Treated Sewage Effluent for Irrigation of Abdally Farms

Clients:
Ministry of Public Works
Contract No.:
SE/59
Project Value (KD):
31,566,577
Commencement Date:
May 20, 2002
Completion Date:
Sep 01, 2004

Pump Station, Reservoir, Administration Building and ...

Read More

Construction of Transmission Mains from Mutla High to West Funaitees (C4) Subiya Water Distribution Scheme Works - Stage I

Clients:
Ministry of Electricity & Water
Contract No.:
MEW/MC/2805/02-03
Project Value (KD):
7,559,242
Commencement Date:
Feb 22, 2003
Completion Date:
Aug 21, 2004

Construction of Transmission Mains from Mutla High to ...

Read More